Call Center Plus:Office Addition
House prior to addition
It's a rainy day and we are getting ready to start the project


Excavator starting to remove driveway: Thursday Oct 21st


Digging the hole for the footings: Friday Oct 22nd


Setting the forms for the footings: Saturday Oct 23rd


Pouring the footings: Monday Oct 25th


Forms set (Monday Evening) and ready for concrete


Pour foundation concrete: Tuesday Oct 26th


Strip foundation: Wednesday Oct 27th, Backfill inside foundation wall, rough plumbing: Thursday and Friday Oct 28 and 29th


Get floor ready to pour: Saturday Morning, Oct 30th


Floor poured: Saturday Afternoon, Oct 30th


It's ready for rain: Saturday Evening, Oct 30th


Siblings, Mother and Self and 75th Birthday Celebration: Saturday, Oct 30th


Backfill Other Side Foundation: Morning Nov 1stM


Backfilling Complete: Morning Nov 1st


Backhoe back, all the mud gone, finally: Late Morning, Nov 1st


Driveway ready for concrete: Afternoon, Nov 1st


Pouring Driveway: Later Afternoon, Nov 1st


Driveway done, 6:30 PM Nov 1st


Begining Framing: Saturday Nov 6th


Walls Up: Saturday Nov 6th


Sunday Morning Views, from the front: Nov 7th


Other Side: Nov 7th


Inside: Nov 7th


Walkway into office: Nov 7th


Trusses are up: Nov 9th


Outside framing complete: Nov 9th


Starting tar paper: Nov 10th


Ready for Shingles: Nov 16th


Inside: Nov 16th


More Inside: Nov 16th


Sheetrock Garage Side: Nov 20th


Storage Area: Nov 20th


Window in, Shingles Complete: Nov 20th


Removing Wall:Dec 4th


A Room Full of Dust:Dec 4th


The Wall is Gone:Dec 4th


Inside Wall: Dec 12th


Starting Siding: Dec 14th


More Siding: Dec 15th


Siding Almost Done: Dec 17th


Siding Complete: Dec 18th